Most builders know "10 percent". It is not 10 percent everywhere, the clock starts on different events, and Ontario changed its release rules on 1 January 2026. This guide sets out what each act actually says, with the section to read. It is general information, not legal advice: your contract and your lawyer govern a real job.
General information for Canadian builders, not legal, tax or accounting advice. Rules change and every contract is different. For a decision that matters, check the source linked here and speak to a lawyer or accountant in your province.
What holdback is, and why it exists
Holdback is a part of every progress payment the payer keeps back while the job is under way. It exists because of builders’ liens. A sub-trade or supplier who is not paid can claim a lien against the owner’s land even though the owner never hired them. The holdback is the owner’s protection: in the common-law provinces, an owner who has kept back the right holdback and pays it out only after the lien period runs out has, in general, limited its exposure to the amount of that holdback.
For a general contractor it works in both directions. Your client holds back from you, which is a big part of your profit sitting in someone else’s account until the end of the job. And you, in turn, are usually expected to hold back from your own sub-trades, for the same reason the owner holds back from you.
Holdback is not a deposit, not a deficiency allowance and not a warranty reserve. It is a statutory amount with a statutory release date. Mixing it up with any of those is how builders end up arguing about the wrong number.
Every province and territory at a glance
Each row was read from the act itself on the date at the top of this page. Periods run from different events in different places: a certificate of substantial performance, a certificate of completion, completion itself, or abandonment. Read the section before you rely on a date. Special rules for public work, oil and gas, and finishing work after substantial performance are left out unless noted.
Swipe the table sideways to see every column.
| Province or territory | Act | Holdback | How long it is kept | Time to preserve or register a lien |
|---|---|---|---|---|
| British Columbia | Builders Lien Act, SBC 1997, c. 45 | 10% (s. 4) | 55 days after the certificate of completion, or after completion, abandonment or termination if there is none (s. 8) | 45 days after the certificate of completion, or after completion, abandonment or termination (s. 20) |
| Alberta | Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4 | 10% (s. 18) | 60 days from the certificate of substantial performance, or completion if none; 90 days for concrete and for oil and gas wells (s. 18) | 60 days from completion or abandonment; 90 days for concrete and for oil and gas wells (s. 41) |
| Saskatchewan | The Builders' Lien Act, SS 1984-85-86, c. B-7.1 | 10% (s. 34) | 40 clear days after a copy of the certificate of substantial performance is given (s. 43) | An unregistered lien expires 40 clear days after the certificate is given, or after completion or abandonment (s. 49) |
| Manitoba | The Builders' Liens Act, C.C.S.M. c. B91 | 7.5% (s. 24) | At least 60 days after the certificate of substantial performance, completion or abandonment, whichever is first (s. 24) | 60 days after substantial performance or abandonment of the contract (s. 43) |
| Ontario | Construction Act, R.S.O. 1990, c. C.30 | 10% (s. 22) | Released every year on the contract anniversary (s. 26, from 1 January 2026); the rest within 14 days after liens expire or are dealt with (s. 26) | Preserve within 60 days after the certificate of substantial performance is published, or completion, abandonment or termination (s. 31); perfect within 90 days after that (s. 36) |
| Quebec | Civil Code of Québec, arts. 2726 to 2728 | No statutory holdback | Not applicable. The client may withhold for defects (art. 2111) and to pay subs who gave notice (art. 2123) | Legal hypothec lasts 30 days after the work ends; register a notice within those 30 days and serve the owner (art. 2727) |
| New Brunswick | Construction Remedies Act, S.N.B. 2020, c. 29 | 10% (s. 34) | 60 days after the certificate of substantial performance is signed, or after completion, abandonment or termination (s. 47) | 60 days after substantial performance is certified, or completion, abandonment or termination (s. 59; subs s. 60). Residential work needs a notice to owner within 45 days (s. 54) |
| Nova Scotia | Builders' Lien Act, R.S.N.S. 1989, c. 277 | 10% (s. 13) | 60 days after the contract is substantially performed (s. 13) | 60 days after completion or abandonment (s. 24) |
| Prince Edward Island | Mechanics' Lien Act, R.S.P.E.I. 1988, c. M-4 | 20%, or 15% where the work and materials exceed $15,000 (s. 14). Check with the province: its published text is current to 2009 | 60 days after completion or abandonment (ss. 14 and 16) | 60 days from completion or abandonment (s. 24) |
| Newfoundland and Labrador | Mechanics' Lien Act, R.S.N.L. 1990, c. M-3 | 10% (s. 12) | 30 days after completion (substantial performance) or abandonment (s. 12) | 30 days after completion or abandonment (s. 22) |
| Yukon | Builders Lien Act, RSY 2002, c. 18 | 10%, unless the contract says otherwise (s. 6) | 30 days after completion (s. 6) | During the work or within 30 days from completion (s. 20) |
| Northwest Territories | Builders' Lien Act, SNWT 2023, c. 24 (in force 1 September 2025) | 10% (s. 24) | Until every lien that could be claimed against it has expired (s. 28) | A contractor’s lien expires 60 days after the certificate of substantial performance is published, or completion, abandonment or termination (s. 36) |
| Nunavut | Mechanics Lien Act, C.S.Nu., c. M-30 | 10%, unless the contract says otherwise (s. 6) | 45 days after completion (s. 6) | 45 days after the contract is completed, terminated or abandoned (s. 22) |
Holdback and lien periods by province and territory, as read on 5 October 2026 Contracts made before the Northwest Territories act came into force stay under the old Mechanics Lien Act. Ontario contracts made before 1 January 2026 have their own transition for the annual release (s. 87.4). Periods in Saskatchewan are clear days. This table is a starting point for a conversation with your lawyer, not a substitute for one.
The two numbers that are not 10 percent
Manitoba is 7.5 percent. Section 24(1) of The Builders’ Liens Act says the payer must "deduct 7.5% of each payment" and keep it for at least 60 days. A lot of templates, accounting setups and US-built software default to 10, which in Manitoba over-holds by a third and leaves the extra in the wrong place.
Prince Edward Island is higher, not lower. Section 14 of its Mechanics’ Lien Act sets 20 percent, dropping to 15 percent where the value of the work and materials is over $15,000. The only version the province publishes online is an office consolidation current to 1 January 2009, so confirm the current figure with the PEI Legislative Counsel Office or your lawyer before you rely on it.
Yukon and Nunavut are 10 percent, but both acts say "in the absence of a stipulation to the contrary", so the contract can change it.
Ontario: annual release from 1 January 2026
Ontario rewrote its release rules. From 1 January 2026 the old sections on paying holdback at substantial performance (26.1 and 26.2) and on notices of non-payment of holdback (27.1) are repealed. In their place, section 26 makes the release yearly.
Within 14 days after each anniversary of the contract, the owner must publish a notice of annual release of holdback. At least 60 and no more than 74 days after that notice, the owner pays the contractor the holdback for the year just ended, unless a lien has been preserved or perfected. The contractor then has 14 days to pay its subs their share. Holdback still owing at the end of the job is paid within 14 days after the liens have expired or been dealt with.
If your contract was signed before 1 January 2026, section 87.4 sets out how the first annual release applies to it. Read it, or ask your lawyer, before you plan cash flow around a release date.
Trust obligations: the money is not yours yet
In most provinces, money a contractor receives on a job is held in trust for the subs and suppliers on that job until they are paid. Using this month’s draw on Job A to make payroll on Job B can be a breach of trust, and several acts make directors personally liable for it.
Holdback accounts are a separate idea: some acts require the owner to put the holdback itself in a dedicated account. Whether one applies depends on the province and the size of the contract.
- Ontario: owner’s trust (s. 7), contractor and subcontractor trust including holdback (s. 8), and trust money must go through a bank account with records kept (s. 8.1).
- British Columbia: money received by a contractor or subcontractor is a trust fund for those engaged on the improvement (s. 10). Owners must open a holdback account unless the work is under $100,000 or the owner is government (s. 5).
- Saskatchewan: trusts at owner, contractor and subcontractor level (ss. 6 to 8), and a holdback trust account in most cases (s. 38), with exemptions including contracts on a house.
- Manitoba: contract money received is a trust fund (s. 4). A holdback account is required above a prescribed amount (s. 24(3)), set at $200,000 by Regulation 127/89.
- Alberta: the trust is narrower, covering money paid after a certificate of substantial performance (s. 22).
- New Brunswick: owner and contractor trusts (ss. 11 and 14), with directors personally liable (s. 17).
- Nova Scotia: owner and contractor trusts (ss. 44A and 44B).
- Northwest Territories: contractor and subcontractor trust (s. 9), deposited to a bank account (s. 10).
- Newfoundland and Labrador, Prince Edward Island, Yukon and Nunavut: we found no trust provisions in the lien acts themselves. Ask a lawyer whether other law applies to your situation.
Holding back from your own sub-trades
Ontario’s section 22(1) puts the duty on "each payer upon a contract or subcontract". BC’s section 4(1) names "the person primarily liable on each contract, and the person primarily liable on each subcontract". In those provinces, you hold back from your subs the same way your client holds back from you.
Not every act is written that way. Manitoba’s section 24 and New Brunswick’s section 34 speak of the contract with the owner. Even so, the commercial logic is the same everywhere: if you pay a sub 100 percent and that sub has not paid its own supplier, the supplier’s lien lands on your client’s property and the argument lands on you. Most builders hold back from subs at the same rate they are held back, and release it on the same timeline. Ask your lawyer how your province’s act applies to your subcontracts.
Before you release a sub’s holdback, check the lien registry for the property and collect whatever your contract requires, commonly a statutory declaration that the sub’s own workers and suppliers are paid.
Substantial performance and completion
Substantial performance is the event that starts most of these clocks. Most acts define it with a sliding test: the work is ready for use, and what is left to finish costs no more than a set percentage of the contract price. The bands differ, so a $1.5 million job can be substantially performed in one province and not in the next.
- Ontario: 3% of the first $1,000,000, 2% of the next $1,000,000, 1% of the balance (s. 2).
- British Columbia, Alberta and Saskatchewan: 3%, 2% and 1% on $500,000 bands.
- Manitoba, New Brunswick and Newfoundland and Labrador: 3%, 2% and 1% on $250,000 bands.
- Nova Scotia: a flat 2.5% of the contract price (s. 13).
- Northwest Territories: 3%, 2% and 1% on $1,000,000 bands, set by regulation.
- Prince Edward Island, Yukon and Nunavut: no percentage test in the act. Periods run from completion.
- In BC the release clock runs from a certificate of completion. In several provinces it runs from a certificate of substantial performance that has to be given or published in a set way. If nobody issues the certificate, the clock may run from completion instead, which can be much later.
Quebec: a legal hypothec, not a holdback
Quebec has no builders’ lien act and no statutory holdback for private work. The Civil Code gives the architect, engineer, supplier of materials, workman, contractor and subcontractor a legal hypothec on the building for work the owner asked for (art. 2726). It exists without being published, but only for 30 days after the work is completed. To keep it, you register a notice within those 30 days and serve it on the owner, and it is extinguished six months after completion unless you take the next legal step (art. 2727).
It secures only the increase in value given to the building. And if you do not have a contract with the owner, as a sub-trade usually does not, it covers only work and materials supplied after you gave the owner written notice of your contract (art. 2728). That notice, the dénonciation de contrat, is the step sub-trades most often miss.
What clients do withhold in Quebec comes from the contract and from articles 2111 and 2123: amounts for defects noted at acceptance, and enough to pay workers and subs who gave notice until the client has proof they were paid. Public bodies have their own withholding rules. Ask a Quebec lawyer or notary about any real hypothec question.
How Ridgepole handles holdback
Every progress claim withholds holdback before tax. The percentage starts from a table of provincial figures, each naming the act and section it was read from, and you can change it for your company or for a single job. Treat it as a starting point: the holdback that applies is the one in your contract and your act. In Quebec and the territories, it asks you for the holdback your contract sets.
You record the substantial performance date on the job. Ridgepole adds the release period for your province, which you can also change, and shows the date the holdback can be released. You get a notification when that date arrives. On Ontario jobs it also shows the yearly release. When you bill the release, it raises a holdback release invoice, whole or partial, and charges the tax then, at the rates of the claims that withheld it.
Holdback works in both directions. Each sub-trade contract carries a holdback percentage, pre-filled the same way. Every payment you log withholds it, and you release it when you are ready. If no unconditional waiver is on file for that sub, the release screen warns you.
On the Enterprise plan, with QuickBooks Online connected, holdback keeps its own accounts in your books. Each claim goes in with its holdback as a negative line to Holdback Receivable and the release invoice clears it; holdback kept from a sub-trade goes to Holdback Payable and its release pays it off. Holdback withheld before your QuickBooks start date is listed job by job for your accountant to enter as an opening balance.
Common questions
Is holdback 10 percent everywhere in Canada?
No. Manitoba is 7.5 percent. Prince Edward Island’s act sets 20 percent, or 15 percent above $15,000 of work (check the current text with the province). Quebec has no statutory holdback at all. Most of the rest are 10 percent, and in Yukon and Nunavut the contract can say otherwise.
When can I bill the holdback?
When the period in your act has run out after the triggering event, usually substantial performance or completion, and no lien has been registered or preserved against it. In Ontario, holdback on longer contracts is also released every year from 1 January 2026. Check the lien registry before you release anything to your own subs.
Do I have to hold back from my subs?
In Ontario and BC the act puts the duty on every contract and subcontract. Other acts are framed around the contract with the owner, but paying a sub in full still leaves you exposed if that sub does not pay its own suppliers. Ask your lawyer how your act applies, and hold back at least at the rate you are held back.
Is holdback money mine while it is in my account?
In many provinces, no. Money received on a job, including holdback once it is paid to you, is commonly a trust fund for the subs and suppliers on that job until they are paid. The sections are listed above. A lawyer can tell you what that means for your bank accounts.
What replaces holdback in Quebec?
A legal hypothec under the Civil Code. It lasts 30 days after the work is completed unless you register a notice and serve the owner, and sub-trades must give the owner written notice of their contract to be covered. Clients may still withhold amounts under the contract and the Code.
Is this legal advice?
No. It is general information read from the acts on the date shown, for orientation. Laws change and the facts of a job matter. Speak to a construction lawyer before you rely on a date or a percentage.
Sources
- Builders Lien Act, SBC 1997, c. 45 (opens in a new tab)British Columbia, ss. 1, 4, 5, 8, 10, 20; current to 22 September 2026
- Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4 (opens in a new tab)Alberta, ss. 2, 18, 22, 41; consolidated to 1 April 2025
- The Builders' Lien Act, SS 1984-85-86, c. B-7.1 (opens in a new tab)Saskatchewan, ss. 3, 6 to 8, 34, 38, 43, 49
- The Builders' Liens Act, C.C.S.M. c. B91 (opens in a new tab)Manitoba, ss. 2, 4, 24, 43; read 5 October 2026
- Builders' Liens Regulation, Man. Reg. 127/89 (opens in a new tab)Manitoba, s. 2: holdback account threshold of $200,000
- Construction Act, R.S.O. 1990, c. C.30 (opens in a new tab)Ontario, ss. 2, 7, 8, 8.1, 22, 26, 31, 36, 87.4; consolidation from 1 January 2026
- Civil Code of Québec (opens in a new tab)Quebec, arts. 2110, 2111, 2123, 2726 to 2728; updated to 12 August 2026
- Construction Remedies Act, S.N.B. 2020, c. 29 (opens in a new tab)New Brunswick, ss. 7, 11, 14, 17, 34, 47, 54, 59, 60
- Builders' Lien Act, R.S.N.S. 1989, c. 277 (opens in a new tab)Nova Scotia, ss. 13, 24, 44A, 44B
- Mechanics' Lien Act, R.S.P.E.I. 1988, c. M-4 (opens in a new tab)Prince Edward Island, ss. 14, 16, 24; office consolidation current to 1 January 2009
- Mechanics' Lien Act, R.S.N.L. 1990, c. M-3 (opens in a new tab)Newfoundland and Labrador, ss. 2, 12, 22
- Builders Lien Act, RSY 2002, c. 18 (opens in a new tab)Yukon, ss. 6, 20
- Builders' Lien Act, SNWT 2023, c. 24 (opens in a new tab)Northwest Territories, ss. 2, 9, 10, 24, 28, 36, 93, 94; in force 1 September 2025
- Mechanics Lien Act, C.S.Nu., c. M-30 (opens in a new tab)Nunavut, ss. 6, 22; consolidation current to 31 May 2024
More guides
- Sales tax on construction in CanadaGST, HST, PST, RST and QST rates by province, the $30,000 small supplier test, tax on holdback, how BC, Manitoba and Saskatchewan treat contractors, input tax credits and new housing rebates.
- Builders’ liens and prompt payment in CanadaHow liens work at a high level, which provinces have prompt payment in force today, the 28-day and 7-day rules, adjudication, and why written change orders and records decide disputes.
- Workers’ compensation clearances for sub-tradesWhat a WSIB, WCB, WorkSafeBC or CNESST clearance is, why a general contractor can be billed for a sub’s unpaid premiums, how often to re-check, and the rules for independent operators.
Software that already knows these rules.
Start free. 14 days to decide. Questions go straight to someone who knows Ridgepole inside out.
14 days free. No credit card. Use it on a real job. Cancel any time, there is no contract and no exit interview.