Builders’ liens and prompt payment

Two sets of rules decide whether you get paid on time: lien law, which protects you when payment fails, and prompt payment law, which sets deadlines so it fails less often. Four provinces now have private-sector prompt payment in force, one more has passed it, and the deadlines are strict. This is general information, not legal advice.

General information for Canadian builders, not legal, tax or accounting advice. Rules change and every contract is different. For a decision that matters, check the source linked here and speak to a lawyer or accountant in your province.

How builders’ liens work

Outside Quebec, every province and territory has a lien act. If you supply work, services or materials to improve land and are not paid, you can claim a lien against the owner’s interest in that land, whether or not the owner hired you directly. It is a security interest: it can stop a sale or a mortgage advance until it is dealt with.

The deadlines are short and they do not bend. A lien must be preserved or registered within a set number of days after a triggering event, and then enforced by starting a court action within a further period, or it expires. In Ontario a lien is preserved within 60 days and perfected within 90 days after that. In Newfoundland and Labrador and in Yukon the registration window is 30 days. The holdback guide has every province’s period and section.

How much a lien actually recovers depends on the holdback the owner kept and on what was still owing. That is why holdback, trust rules and liens are best read together. Quebec uses a legal hypothec under the Civil Code instead, covered in the holdback guide.

Do not register a lien without advice. A lien registered late, against the wrong property or for an inflated amount can leave you paying the owner’s costs.

Prompt payment: where it is in force

Prompt payment laws make payment deadlines statutory. The pattern is the same where they exist. The contractor gives the owner a proper invoice, usually monthly. The owner pays within 28 days or gives a notice saying what it disputes. The contractor then has a short window to pay its subs, or to give its own notice. Disputes can go to a fast adjudication rather than to court.

Swipe the table sideways to see every column.

Private-sector construction prompt payment, status on 5 October 2026
JurisdictionIn forceOwner pays a proper invoiceContractor pays subsAdjudication
OntarioYes. Construction Act, Parts I.1 and II.1Within 28 days, or notice of non-payment within 14 days (s. 6.4)Within 7 days of being paid; 35 days after invoicing if the owner does not pay, unless notice is given (s. 6.5)ODACC
AlbertaYes. Prompt Payment and Construction Lien Act, Part 3 and Part 5Within 28 days, or notice of dispute within 14 days (s. 32.2)Same 7-day and 35-day pattern (s. 32.3)A nominating authority; ARCANA (ADR Institute of Alberta) says it is designated
SaskatchewanYes. The Builders' Lien Act, Parts I.1 and II.1Within 28 days, or notice within 14 days (s. 5.4)Within 7 days, with a 35-day fallback (s. 5.5)Saskatchewan Construction Dispute Resolution Office (SCDRO)
ManitobaYes, for contracts made on or after 1 April 2025. The Builders' Liens Act, ss. 79 to 125Within 28 days, or notice of non-payment within 14 days (s. 90)Within 7 days of being paid (s. 92), with a 35-day fallback (s. 93)Manitoba Prompt Payment Adjudication Authority
British ColumbiaNo. Construction Prompt Payment Act, SBC 2025, c. 24, passed but not in forceNot yet in forceNot yet in forceNot yet in force
Nova ScotiaNo. 2019 and 2022 amendments not proclaimedNot in forceNot in forceNot in force
QuebecPublic contracts only, phased in from 8 September 2026 for smaller contractsBy the end of the month the payment request is receivedBy the 5th of the second month afterA third-person decider under the public contracts regulation
New Brunswick, Newfoundland and Labrador, Prince Edward IslandNone found in the lien actsCheck with the provinceCheck with the provinceNone found
Yukon, Northwest Territories, NunavutNot confirmedCheck with the territoryCheck with the territoryCheck with the territory

Private-sector construction prompt payment, status on 5 October 2026 In every province where it is in force, prompt payment applies only to contracts made after the regime began, so the date your contract was signed matters. Work on federal real property has its own regime under the Federal Prompt Payment for Construction Work Act, in force 9 December 2023, which defers to the provincial regime in Ontario, Saskatchewan and Alberta.

Ontario in more detail

Proper invoices go to the owner monthly unless the contract says otherwise (s. 6.3). A clause making the invoice conditional on an architect’s certificate or the owner’s prior approval has no effect. A proper invoice must contain set information: your name and address, the date and the period it covers, the contract it relates to, a description of what was supplied, the amount and payment terms, and where to send payment (s. 6.1).

Since 1 January 2026, an invoice that is missing something is deemed proper unless the owner tells you in writing within 7 days what is wrong and what is needed (s. 6.1(2)). The owner pays within 28 days, or gives a notice of non-payment within 14 days that sets out the amount it will not pay and all of its reasons (s. 6.4).

When you are paid, you pay your subs their share within 7 days. If the owner does not pay, you still pay your subs by day 35 after you invoiced, unless you give them a notice of non-payment that undertakes to refer the dispute to adjudication (s. 6.5).

Adjudication through ODACC is quick: the adjudicator decides within 30 days after receiving the documents, and an amount awarded must be paid within 15 days of the decision (s. 13.19). The decision binds until a court, an arbitrator or the parties’ written agreement says otherwise. From 2026, an adjudication on a contract can start up to 90 days after the contract is completed, abandoned or terminated (s. 13.5).

Alberta, Saskatchewan and Manitoba

All three copied the Ontario shape: monthly proper invoices (Alberta says at least every 31 days), 28 days for the owner, 14 days to dispute, 7 days to pay subs, and 30-day adjudication decisions. The differences are in the details, the names of the notices and the adjudication bodies.

Manitoba is the newest. Its prompt payment division came into force on 1 April 2025 and applies to contracts and sub-contracts made on or after that date (s. 80). Adjudication runs through the Manitoba Prompt Payment Adjudication Authority, decisions are due within 30 days, and an award is payable within 10 days.

Alberta adjudication must start within 30 days of final payment (s. 33.4). Saskatchewan adjudications run through SCDRO. Each province’s start date and transition rules decide whether your contract is covered, so check the date your contract was made against the act.

Why written change orders and records decide disputes

Prompt payment shortens every argument to a few weeks. A notice of non-payment must give reasons, and an adjudicator decides on the documents in front of them within about a month. The builder with signed change orders, dated daily logs and a clean invoice history wins those. The builder with a text message saying "go ahead with the extra framing" usually does not.

Liens work the same way. The amount you can claim is what you can show you supplied and were not paid for. An unsigned extra is a dispute about whether it was ever part of the contract.

  • Get every change signed before the work is done, with the price and the effect on the schedule.
  • Keep a daily log: who was on site, what was done, weather, delays and their causes, with photos.
  • Invoice on a regular cycle, with the information a proper invoice needs, and keep the date you sent it.
  • Diarize the 14-day and 7-day notice windows the day an invoice goes out. Missing a notice can cost you the right to dispute.
  • Keep the date of substantial performance and of your last supply. Lien periods run from them.

How Ridgepole keeps the record

Ridgepole keeps the records these disputes turn on. A go-ahead records who said yes to an extra, how and when, the day it happens. Change orders are priced line by line, signed by the client online or on paper, and become part of the contract value when approved, with a PDF of each one. Daily logs record weather, crew and trades on site, notes and photos, and can be written with no signal. Progress claims and invoices are numbered and dated, with your tax registration numbers on them, and files live in each job’s Documents.

Invoices take their due dates from your payment terms. Each morning anything past due is marked overdue and your team is told, and on the day a job’s holdback release date arrives your owners and admins get a notice. When a dispute comes, the signed change orders, the dated logs and the invoice history are in one place to hand to your lawyer or an adjudicator.

Common questions

Which provinces have prompt payment for private construction?

As of 5 October 2026: Ontario, Alberta, Saskatchewan and Manitoba. British Columbia has passed an act that is not yet in force, and Nova Scotia’s amendments have not been proclaimed. Quebec’s rules cover public contracts only. Each regime applies to contracts made after its start date.

What happens if the owner does not pay in 28 days?

Unless the owner gave a valid notice of non-payment in time, the amount is overdue under the act and you can refer the dispute to adjudication, which decides in about a month. In Ontario you may also have rights to interest and to suspend work after an unpaid adjudication award. Get advice on your specific case.

Do I have to pay my subs if the owner has not paid me?

In Ontario, Alberta, Saskatchewan and Manitoba, generally yes, by day 35 after you invoiced, unless you give your subs the notice the act requires in time, which in Ontario includes undertaking to refer the dispute to adjudication. Check the exact notice and timing in your act.

Is an adjudicator’s decision final?

It is binding in the meantime, and must be paid on a short timeline, until a court, an arbitrator or a written agreement between the parties decides otherwise. Most disputes end there.

How does Ridgepole help when a payment is disputed?

It keeps the documents an adjudicator decides on: go-aheads with who said yes, signed change orders, dated daily logs with photos, and numbered, dated invoices with overdue ones flagged. Diarize your act’s notice windows the day each invoice goes out.

Is this legal advice?

No. It is general information read from the acts and the adjudication bodies on the date shown. Speak to a construction lawyer about a real dispute.

Sources

  1. Construction Act, R.S.O. 1990, c. C.30 (opens in a new tab)Ontario, ss. 6.1 to 6.6, 13.5, 13.13, 13.15, 13.19, 31, 36; consolidation from 1 January 2026
  2. Ontario Dispute Adjudication for Construction Contracts (ODACC) (opens in a new tab)Ontario, authorized nominating authority
  3. Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4 (opens in a new tab)Alberta, ss. 32.1 to 32.3, 33.4, 33.6, 74; consolidated to 1 April 2025
  4. ADR Institute of Alberta: prompt payment (opens in a new tab)Alberta, ARCANA designation as a nominating authority
  5. The Builders' Lien Act, SS 1984-85-86, c. B-7.1 (opens in a new tab)Saskatchewan, ss. 5.3 to 5.5, 21.5, 21.52, 105.1
  6. Saskatchewan Construction Dispute Resolution Office (opens in a new tab)Saskatchewan adjudication
  7. The Builders' Liens Act, C.C.S.M. c. B91 (opens in a new tab)Manitoba, ss. 79 to 125, in force 1 April 2025; s. 43
  8. Manitoba Prompt Payment Adjudication Authority (opens in a new tab)Manitoba adjudication
  9. Federal Prompt Payment for Construction Work Act (opens in a new tab)Federal real property only, in force 9 December 2023
  10. Nova Scotia: proclamations of statutes (opens in a new tab)Nova Scotia, Builders' Lien Act amendments 2019, c. 12 and 2022, c. 43 not proclaimed
  11. BC Laws (opens in a new tab)British Columbia, Construction Prompt Payment Act, SBC 2025, c. 24, listed as not in force on 22 September 2026
  12. Quebec regulation on prompt payments for public construction contracts, C-65.1, r. 8.001 (opens in a new tab)Quebec, public bodies only; phase-in from 8 September 2026

Software that already knows these rules.

Start free. 14 days to decide. Questions go straight to someone who knows Ridgepole inside out.

14 days free. No credit card. Use it on a real job. Cancel any time, there is no contract and no exit interview.